Los Angeles ports

Container landed at Long Beach: steps before a truck can load

Published 9 min readBy LA Freight Group

Short answer

A domestic truck can load only after the container is released, its port fees are paid, a drayage carrier has pulled it on a terminal appointment and the transload warehouse has unloaded it. Import containers leaving Los Angeles and Long Beach by truck sat an average of 3.60 days on the terminal in October 2026, so book the truck against the warehouse's confirmed ready time.

  • Local truck dwell at the San Pedro Bay terminals averaged 3.60 days in October 2026, up from 3.18 days in September and 2.95 days in August.
  • An appointment is required to pick up any import container, in a two-hour window, with last appointments at 3:30 p.m. and 1:30 a.m.
  • A 40-foot container cannot leave until the $81.26 Traffic Mitigation Fee and the $20 Clean Truck Fund rate are paid, $101.26 in total.
  • Only 2 of the 12 terminals list a regular Friday night gate and none lists a regular Saturday or Sunday shift in the August 1, 2026 schedule.
  • Published carrier tariffs allow dry import containers 4 working days of free time at the terminal before demurrage starts.

A domestic truck cannot load import freight until four things have happened to the container: it has been released, its port fees have been paid, a drayage carrier has pulled it from the terminal on an appointment, and a transload warehouse has unloaded it. Containers leaving the Los Angeles and Long Beach terminals by truck sat an average of 3.60 days on the terminal in October 2026, before any of the trucking or warehouse work began. The outbound truck should be booked against the warehouse's confirmed ready time, never against the vessel's estimated arrival.

The steps, who owns each one and what delays it

StepWho does itWhat has to be trueWhat delays it
1. Vessel dischargeOcean carrier and terminalContainer is off the ship and in the yard. Free time starts at about 3:00 a.m. after dischargeLate vessel, berth wait
2. ReleaseCustoms broker, importer, ocean carrierCustoms hold lifted, carrier's charges settledExam, missing documents, unpaid charges
3. Port feesImporter or its agentTMF of $81.26 and CTF rate of $20 per 40-foot container cleared. Any demurrage paidPayment not posted, suspended account
4. Terminal appointmentDrayage carrierA two-hour pickup window booked with that terminalNo slots, closed shift, holiday week
5. Dray to the warehouseDrayage carrierTruck, driver and chassis at the terminal inside the windowMissed window, chassis shortage, road closures
6. Unload and palletizeTransload warehouseFreight counted, sorted and on palletsWarehouse queue, shortages, damage
7. Domestic pickupShipper and its freight brokerReady time, pallet count, dimensions and weight confirmedTruck booked before the freight is ready

Fee amounts: WCMTOA Schedule No. 1, effective August 1, 2026, and PortCheck. Appointment rule: WCMTOA Schedule No. 1, Rule 5(C). Free-time start: COSCO SHIPPING Lines and Maersk import tariffs. Checked 28 November 2026.

The first six steps belong to other companies. A customs broker handles the entry. A drayage carrier handles the terminal and the short haul. A warehouse handles the unload. The domestic freight broker enters at step 7, and the handoff between step 6 and step 7 is where the outbound plan usually fails. How the unload and reload work is covered in transloading at the ports of LA and Long Beach.

How long containers sit before a truck takes them

The Pacific Merchant Shipping Association publishes the average time import containers stay on the San Pedro Bay terminals each month. The figures for containers leaving by local truck rose through the autumn peak.

MonthLocal truck dwellRail dwell
August 20262.95 days6.75 days
September 20263.18 days7.19 days
October 20263.60 days8.16 days

Source: Pacific Merchant Shipping Association, San Pedro Bay Ports Container Dwell Times, published October 15 and November 16, 2026.

Local truck dwell of 3.60 days is an average across the Los Angeles and Long Beach terminals, so some containers leave on the first day and others wait a week. Set that average against free time. COSCO SHIPPING Lines and Maersk both publish 4 working days of free time for dry import containers at these ports, after which demurrage runs at $165 per day (COSCO, effective August 14, 2026) or $300 per day (Maersk, effective June 20, 2026) in the first tier. An average container in October left very little of that free time unused by the time it reached the gate.

Release: holds that keep a container on the terminal

A container that is physically available can still be on hold. PortCheck, which collects the Clean Truck Fund rate for the two ports, notes that after its own hold clears "there may be other HOLDS that the terminal has placed on this container, such as demurrage, customs, etc." Each hold has a different owner. The customs broker clears a customs hold. The importer or forwarder settles the ocean carrier's charges. Demurrage, if free time has already expired, has to be settled before release: Total Terminals International at Long Beach tells users to make the payment before the container is released.

None of these is visible to a domestic trucking company, and none can be fixed by one. Ask the customs broker and the drayage carrier for the container's status. The vessel-tracking page only shows where the ship is.

Fees that must clear before the gate opens

Two fixed fees have to be paid on every loaded import container that leaves a Los Angeles or Long Beach terminal by truck, unless an exemption applies.

  • Traffic Mitigation Fee. $40.63 per 20-foot container and $81.26 for every other size, effective August 1, 2026. The terminal operators' schedule says the fee on import cargo must be paid before the container leaves the terminal. Fenix Marine Services at the Port of Los Angeles adds that the fee does not have to be cleared when the appointment is made, but it must be cleared before the driver arrives.
  • Clean Truck Fund rate. $10 per TEU and $20 for every other size, collected since April 1, 2022. PortCheck states that the ports require terminals to place a hold on the container until the rate is paid, and that the hold can take up to one hour to release after payment.

The two fees come to $101.26 on a 40-foot container. The cargo owner or its agent pays both, and a payment made late on the day of the appointment can cost the appointment. The full list of charges is in every fee on an import container at LA and Long Beach.

The terminal appointment and the gate hours behind it

An appointment is required to enter any of the 12 container terminals to pick up an import container. Rule 5(C) of the terminal operators' schedule, revised August 1, 2026, sets appointment windows at two hours including any grace period, and sets the last appointment times for the first and second shifts at 3:30 p.m. and 1:30 a.m. Appointments are made with each terminal under that terminal's own terms. Fenix Marine Services, for example, books in 30-minute blocks and cancels a missed appointment immediately.

Gate hours decide how many windows exist. The schedule defines peak hours as 3:00 a.m. to 5:59 p.m. Monday to Friday and lists off-peak gates from 6:00 p.m. to 2:59 a.m. on Monday, Tuesday, Wednesday and Thursday nights. In the schedule's shift table, only APM Terminals and SSA Terminals show a Friday night gate, SSA Terminals shows no Wednesday night gate, and no terminal shows a regular Saturday or Sunday shift. Terminals may change a shift on 14 days' public notice and may add or drop off-peak gates at any time.

The practical effect is a weekend gap. A container released on a Thursday afternoon may not have an open window until Monday. Holiday weeks shrink the calendar further: PierPass told users on November 20, 2026 to check each terminal's website for its Thanksgiving-week gate schedule. Terminals do add gates. The Port of Long Beach said its terminals would offer extra evening and Saturday gates for six weeks from late October, excluding Thanksgiving week, around the Vincent Thomas Bridge closure that began November 7. The rules are set out in terminal appointments at Los Angeles and Long Beach.

The dray, the unload and the reload

The drayage carrier's truck has to reach the terminal inside the appointment window with a chassis for the container. Once the container is through the out-gate, demurrage stops. The ocean carrier's detention clock and the chassis rental then run until the empty container and the chassis are returned. That gives the importer a reason to have the warehouse unload quickly, and it has nothing to do with whether the outbound truck is ready.

At the warehouse, the container waits its turn for a door. Floor-loaded cartons are unloaded by hand, checked against the packing list, sorted and stacked on pallets. Only at the end of that work does anyone know the real pallet count, the pallet dimensions and the weight, which are the three figures a domestic carrier needs to price and plan the load.

When to book the truckload or LTL pickup

Book the domestic truck when the transload warehouse confirms a ready time. A date that depends on the vessel, the customs release or the terminal appointment can still slip.

What to have in hand before requesting the pickup:

  • The warehouse's confirmed ready date and time, its shipping hours and whether it loads by appointment.
  • Final pallet count, pallet dimensions including height, and total weight.
  • Whether the pallets can be stacked.
  • The delivery address, receiving hours and appointment requirement at the destination.

A full truckload is usually booked for a specific pickup window at the warehouse, so the ready time needs to be firm. An LTL pickup needs the same pallet figures, and it needs the freight staged and labeled before the driver arrives. In both cases a truck that arrives before the freight is ready starts the clock described in detention, layover and TONU charges.

LA Freight Group is run from Los Angeles and books the domestic truck leg from the transload warehouse to the destination. Request a quote when the warehouse has given you the ready time and the pallet details.

Sources

Questions

Related questions

How long after a ship arrives at Long Beach can a domestic truck pick up the freight?

There is no fixed number. Containers leaving the Los Angeles and Long Beach terminals by truck waited an average of 3.60 days on the terminal in October 2026, and the dray, the unload and the palletizing come after that. The reliable trigger is the transload warehouse's confirmed ready time, not the vessel's arrival date.

What has to be paid before a container can leave a Los Angeles or Long Beach terminal?

The PierPass Traffic Mitigation Fee, $81.26 on a 40-foot container since August 1, 2026, and the Clean Truck Fund rate, $20 on a 40-foot container, must both be cleared, along with any demurrage owed. Terminals also keep a hold on a container until customs has released it.

Can a container be picked up from the port on a weekend?

Rarely on a regular schedule. In the terminal operators' schedule revised August 1, 2026, off-peak gates run 6:00 p.m. to 2:59 a.m. Monday to Thursday, only two terminals list a Friday night gate and none lists a regular Saturday or Sunday shift. Terminals post extra gates week by week, so the drayage carrier checks each terminal.

Should I book the outbound truck when the vessel arrives?

No. A vessel arrival date says nothing about customs release, appointment availability or the warehouse's unload queue. Book the truckload or LTL pickup when the transload warehouse confirms the freight is unloaded and gives a ready time with a pallet count and weight. A truck sent too early waits and bills detention.

Does LA Freight Group arrange the drayage or customs clearance?

No. A customs broker files the entry and a drayage carrier pulls the container from the terminal and returns the empty. LA Freight Group is run from Los Angeles and books the domestic truck leg: the truckload, partial or LTL shipment from the transload warehouse to the destination.

Keep reading